Oops

The original plan was to pour the concrete piers for the house, build the carport and shop and then move the shop and house containers over to the property in a nice orderly manner.  The shop landlord is selling the property so we have until March 15 to be out.  So we opted for full chaos moving as a new plan.  We moved the first of 8 containers onto the property only to realize we had blocked the access to the power pole that APS will need to set us up with a temporary construction power meter.  So we got George the crane guy to lift, rotate and move the container 15 feet.